J045--BOILER REPAIR HUDSON VALLEY VAHCS - MONTROSE CAMPUS

Agency
VETERANS AFFAIRS, DEPARTMENT OF / VETERANS AFFAIRS, DEPARTMENT OF
Location
Montrose, NY
Amount
Amount not listed
Posted
Jul 21, 2026
Set-aside
Total Small Business Set-Aside (FAR 19.5)
NAICS code
238220 - Plumbing, Heating, and Air-Conditioning Contractors look up NAICS codes
PSC code
J045

Timeline

  1. Posted

    Jul 21, 2026

  2. Status

    Open now

What contracts like this typically pay

est. $20K

Estimated from 8 similar past awards in New York, NAICS 238220.

This is not this contract’s value. It’s what the government has actually paid for comparable work in the past. How we estimate this.

What this contract is for

Agency
VETERANS AFFAIRS, DEPARTMENT OF / VETERANS AFFAIRS, DEPARTMENT OF
Location
Montrose, NY
Set-aside
Total Small Business Set-Aside (FAR 19.5)
NAICS
238220 - Plumbing, Heating, and Air-Conditioning Contractors
Scope
Federal

Provide the services of a mechanical contractor to replace in kind one (1) existing Webster burner assembly on Boiler #2 in the Boiler Plant (Building 20) at the VA Hudson Valley Healthcare System Montrose Campus.

The Scope of Work also includes the replacement of the existing burner train field devices for both gas and oil and the replacement of existing field devices in the front of the boiler.

All replacement of the field devices must be in kind.

Replace burner air intake manifold and all associated ductwork, fittings, filters, alarms, etc.

Other repairs required are listed below.

All work shall be performed in accordance with attached VA specifications, VA Design Manual, and VA Boiler and Associated Plant Safety Device Testing Manual, Eighth Edition.

Background: Boiler # 2 is a Victory Energy, D-type Water-tube boiler rated at 30,000 lb/hr steam (approximately 37.5MMBtu/h input).

The boiler was originally installed in 2011 with a Webster model HDSXC-105C-9V-750 Burner.

The Micro-Mod Parallel Positioning (Metering) Combustion Controls were installed in a separate project, in 2019.

The burner is equipped for Natural Gas Firing, as well as Number 2 Fuel Oil with the option for either compressed air or steam atomization.

The back-up (Propane) pilot system is via a small (portable) bottle, connected by a temporary hose- when needed.

The Burner Flame Safeguard system is a Fireye YB110, with a Fireye YZ300 Expanded Annunciation Module and a Fireye 45UV5 Scanner- all original to the 2011 project.

Item #1 Replace Boiler #2 Burner Assembly and Controls - The existing Webster Burner for Boiler #2 is damaged from a fire side explosion and shall be replaced in kind as listed as the same model identified in the above background (Webster model HDSXC-105C-9V-750 Burner).

All existing burner fue...

Official solicitation and documents

The full solicitation, any attachments, and the actual submission instructions live on the official listing, not on this page. Oppward summarizes public record data; it does not host or mirror the source documents.

View the official listing on SAM.gov

Oppward is an independent service and is not affiliated with, endorsed by, or sponsored by SAM.gov or any government agency. This page is a plain-English summary of public record data; the linked source above is the authoritative listing.

How to bid on this

This is a contract solicitation, not a grant. To bid, you submit a proposal (usually a price and a description of how you would do the work) directly to the government, through the channel the official listing specifies, not through Oppward.

  1. Make sure your business has an active SAM.gov registration. You cannot be paid on a federal contract without one.
  2. Read the full solicitation on the official listing above, especially the scope of work, not just this summary. Our guide to reading a solicitation walks through what to look for.
  3. Check the set-aside listed above and confirm your business actually qualifies for it before you spend time on a proposal. See our guide to set-asides if the category is unfamiliar.
  4. Submit your proposal by the deadline, using the exact submission method the official listing states. A technically on-time bid sent the wrong way is often treated as late.

Get contracts like this one matched to your business, free.